Russian River’s Biological Opinion Info and Meetings

Add to your long term calendar for preparations and participation:

Attached is the Powerpoint presentation from SCWA staff made to the contractors’ Tech. Advisory Committee on Monday 10/5.

bo_nepa_ceqa_presentationfinal_ppfc_10_01_2008

Please note particularly (@ page 7) the schedule mandated within the B.O. itself for reopening D.1610 and certification of FEIR/FEIS

The B.O. is issued on Sept. 24, 2008.

Biological Opinion Requirements

Permanent Changes
- 2009 File Petition to Change Decision 1610 within 1 Year of Issuance of Biological Opinion
- 2009-2010 Issue NOP/NOI within 6 Months of SWRCB Issuing Public Notice of Petition to Change

Decision 1610
- 2013 SCWA Board of Directors to Certify FEIR/FEIS within 4 Years of Filing Petition to Change Decision 1610

Interim Changes
- 2009-2010 CEQA Document, Petition for Interim Change to Decision 1610
- 2010 Begin Interim Change until Permanent Changes Approved

David

David,

Attached is a pdf version of the NEPA/CEQA presentation given at the October 1, 2008, Public Policy Facilitating Committee meeting.

Regards,

Jessica Martini-Lamb

Principal Environmental Specialist, Wildlife Biologist

Sonoma County Water Agency

P.O. Box 11628

Santa Rosa, CA 95406

707.547.1903

707.524.3782 fax

This entry was posted in Watershed Related Concerns. Bookmark the permalink.